A project team that operates with a full-time project manager as a separate unit from the rest of the organization is structured using ________ organization.

asked
User Panini
by
9.0k points

1 Answer

0 votes

Answer:

E.) Projectized

Step-by-step explanation:

These are the options

A. Functional

B. Balanced matrix

C. Weak matrix

D. Strong matrix

E. Projectized

A project team that operates with a full-time project manager as a separate unit from the rest of the organization is structured using projectized organization.

A projectized organization reffered to as a settings, where activities are arranged in form of projects or even programs and these activities are been executed, these projects are carried out by team with a project manager as their authority in which all the member of the team gives report to.