Monica, a project manager at a software firm, learns during a status report meeting that a difference exists between the baseline scope and the actual project performance. What does Monica need to do next?

1 Answer

4 votes

Answer:

analyze the variance

Step-by-step explanation:

In this scenario, the next necessary step that Monica must take would be to analyze the variance of the scope. Analyzing the variance is done in order to effectively determine whether or not a change in scope is actually warranted, and must be done every time that there is a difference identified between the actual performance and the baseline scope such as in this scenario.