Three teams in the Agile Release Train are working on the same Feature. Team A is a component team, and Teams B and C are feature teams. During PI Planning, Teams B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A’s piece in the first week of the IP Iteration. Why is this an anti-pattern?

asked
User Cosmin D
by
8.5k points

1 Answer

2 votes

Answer:

Correct Answer:

This is an anti-pattern because of the following:

1. The time it would take to plan work for the IP iteration during PI planning

2. The time it would take to wait for the IP iteration to fix defects

3. Too much time that is going to be spent analyzing each features

Step-by-step explanation: