asked 58.5k views
2 votes
the difference between the actual quanity and the standard quanity, multiplied by the standard price is the

1 Answer

2 votes

Answer: Direct materials quantity variance.

Step-by-step explanation:

Direct Material quantity variance is the difference between the actual quantity of materials used in production and the standard quantity that was supposed to be used, multiplied by the standard price of the material.

It is a method that checks the company's efficiency is being able to use raw materials to produce goods. If the Actual quantity needed is greater than the Standard quantity, this will be considered an Unfavorable Variance and mean that the company was not efficient in using the materials.

Causes of this can be low quality of materials and inadequate employee training.