asked 199k views
0 votes
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates, activity time variability with path interdependencies, and resource dependence.

a. True

b. False

1 Answer

1 vote

Answer: True

Step-by-step explanation:

The expected completion time of a project is determined when the duration of every activity that takes place on the critical path is established.

Three phenomena that tend to bias the expected completion time of projects are inflated time estimates, activity time variability with path interdependencies, and resource dependence.