Kaitlyn can build a shed in 6 days. Mark can build the same shed in 8 days. Which equation can be used to find d, the number of days it would take Kaitlyn and Mark to build the shed together? Rate (Sheds per Day) Time (Days) Fraction Completed Kaitlyn One-sixth d One-sixth dd Mark One-eighth d One-eighth dd One-sixth d minus one-eighth d = 48 One-sixth d + one-eighth d = 48 One-sixth d minus one-eighth d = 1 One-sixth d + one-eighth d = 1

2 Answers

0 votes
the awnser would be 1
answered
User Sten Petrov
by
8.0k points
1 vote

Answer:

One-sixth d + one-eighth d = 1

Explanation:

When they work together, their rates of completion add. They want to build one shed, so the number of sheds being built is ...

(Kaitlyn's sheds per day)×(days Kaitlyn works) +(Mark's sheds per day)×(days Mark works) = 1 shed

(1/6)d + (1/8)d = 1 . . . . matches the last choice