Answer:
Hello your question lacks some values here are the values
T1 = 500⁰c, T7 = 70⁰c, Qb = 240000 kj/s
answer : A) 56%
 B) 134400 kw ≈ 134.4 Mw
Step-by-step explanation:
Given values 
T1 (tmax) = 500⁰c = 773 k
T7(tmin) = 70⁰c = 343 k
 Qb = 240000 kj/s
A) Determine the maximum possible efficiency
 = 1 - 
 * 100
 = 1 - ( 343 / 773 ) 
 = 1 - 0.44 = 0.5562 * 100 ≈ 56%
B) Determine the power output for this complex steam power plant design
 = Qb * max efficiency 
 = 240000 kj/s * 56% 
 = 240000 * 0.56 = 134400 kw ≈ 134.4 Mw