John can clear a lot in 1.5 hours. His partner can do the same job in 4.5 hours. How long will it take them to clear the lot working together?

asked
User Nen
by
7.9k points

1 Answer

2 votes

Answer:

1 hour and 7.5 minutes

Explanation:

We have the following information:

Jose makes 1 / 1.5 of the job per hour. It is his rate of work in addition to that the partner makes 1 / 4.5 of the job per hour. It is his rate of work.

Thus:

1 / 1.5 + 1 / 4.5 = 1 / x

0.8898 = 1 / x

x = 1 / 0.8888

x = 1.125

Hence, it will take 1 hour and 7.5 minutes for them to complete the job working together.