asked 207k views
2 votes
At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the information is as follows:

Job

Direct Materials

Direct Labor

Machine Hours

Job 765

$5,670

$3,500

27

Job 766

$8,900

$4,775

44

Job 765 produced 152 units, and Job 766 consisted of 250 units.

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour, determine the (a) balance on the job cost sheets for each job, and (b) the cost per unit at the end of April.

1 Answer

2 votes

Answer:

Instructions are below.

Step-by-step explanation:

Giving the following information:

Job 765:

Direct material= $5,670

Direct labor= $3,500

Machine Hours= 27

Job 766:

Direct material= $8,900

Direct labor= $4,775

Machine Hours= 44

Job 765 produced 152 units, and Job 766 consisted of 250 units.

Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $200 per hour.

Costs sheet:

Job 765:

Direct material= 5,670

Direct labor= 3,500

Allocated overhead= 200*27= 5,400

Total cost= 14,570

Unitary cost= 14,570/152= $95.85

Job 766:

Direct material= 8,900

Direct labor= 4,775

Allocated overhead= 200*44= 8,800

Total cost= 22,475

Unitary cost= 22,475/250= $89.9

answered
User Dave Smits
by
7.7k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.

Categories