Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket in Problem 3. The unit is to be prepared in week 10. The lead times for the components are bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1 week), casting (3 weeks), bearing (1 week), and shaft (1 week).

a) Prepare the time-phased product structure for the bracket.
b) In what week do you need to start the castings?

asked
User Designer
by
8.2k points

1 Answer

5 votes

Answer:

Step-by-step explanation:

A) The time-phased product structure for the bracket is attached as a document.

B) The casting will start on week 5 and week 9.

Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule-example-1
Your boss at Xiangling Hu Products, Inc., has just provided you with the schedule-example-2
answered
User Pono
by
7.6k points

Related questions

1 answer
0 votes
150k views
asked Jul 8, 2024 171k views
Alexandre Heinen asked Jul 8, 2024
by Alexandre Heinen
7.6k points
1 answer
4 votes
171k views
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.