asked 102k views
1 vote
Copy Center pays an average wage of $12 per hour to employees for printing and copying jobs, and allocates $18 of overhead for each employee hour worked. Direct materials are assigned to each job according to actual cost. If Job M-47 used $330 of direct materials and took 20 direct labor hours of labor to complete, what is the total cost that should be assigned to the job?

asked
User Bakkal
by
8.3k points

1 Answer

2 votes

Answer:

Total cost= $930

Step-by-step explanation:

Giving the following information:

Copy Center pays an average wage of $12 per hour.

Overhead rate= $18 per direct labor hour

Job M-47:

used $330 of direct materials and took 20 direct labor hours of labor to complete.

Total cost= direct material + direct labor + allocated overhead

Total cost= 330 + 20*12 + 20*$18= $930

answered
User Jodag
by
8.7k points