An example of fast tracking a project schedule would be to overlap the design and production phases for a design-to-production project, where the conventional approach would be to move on to construction only after completing the design phase.T/F

asked
User Nejc
by
7.5k points

1 Answer

7 votes

Answer: TRUE

Step-by-step explanation:

I just took the test