Washington waterworks manufactures snorkel gear. during the past month, washington purchased 4,000 pounds of plastic to use in its dive masks, at a cost of $6,800. the standard price for the plastic is $1.6 per pound. the company actually used 3,800 pounds of the plastic to produce 15,000 dive masks. calculate washington's direct materials price variance for the mont

asked
User Giladbi
by
7.8k points

1 Answer

3 votes

Answer:

$400 unfavorable variance

Step-by-step explanation:

The standard price of plastic is $1.60 per pound, and if we multiply that by 4,000 pounds purchased = $6,400. But instead of paying $6,400, the company paid $6,800 for the plastic. That means that there was an variance in direct materials of = $6,400 - $6,800 = -$400, since the result is negative, the variance is unfavorable.

An unfavorable variance results from spending money than budgeted to produce the same amount of goods.

answered
User Luismreis
by
7.7k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.