A job cost sheet usually contains a record of each of the following except: Group of answer choices The cost of direct labor charged to a particular job. The overhead costs actually incurred on a particular job. The cost of direct materials charged to a particular job. The overhead cost applied to a particular job.

1 Answer

2 votes

Answer:

The overhead costs actually incurred on a particular job

Step-by-step explanation:

The job cost sheet refer to the sheet in which all the incurred cost are recorded with respect to the direct material cost, direct labor cost, and the manufacturing overhead cost. The manufacturing overhead cost should be recorded as an applied overhead only because it is not available till the year end. Plus it also includes the number of job, name of customer, etc