asked 7.8k views
1 vote
DJ has finished 10% of an art project that has taken him a total of 4 hours so far. If he continues to work at the same rate, how many hours will it take for him to complete the entire project?

asked
User Lateesha
by
8.3k points

1 Answer

3 votes

Answer:

40 hrs

Explanation:

-Given that 10% of the work is done in 4 hrs.

-Determine how many 10% portions make up 100%


=(100\%)/(10\%)\\\\=10

-Given that the work rate is remains unchanged for the entire work period.

#We multiply the number of hours per portion by the total number of portions:


t=hrs* portions\\\\=4* 10\\\\=\ 40\ hrs

Hence, it will take 40 hrs to finish the job.