T takes 10 road workers 5 days to complete a road repair when working 2 hours a day. Working at the same pace, how many days will it take 2 people working 5 hours a day to finish it?

asked
User Jmjr
by
7.7k points

1 Answer

3 votes

Answer:

The no. of days required to finish the work = 10 days

Explanation:

In first case :-

No. of workers
M_(1) = 10

No. of days
D_(1) = 5

No. of hours taken
H_(1) = 2 hours

In second case :-

No. of workers
M_(2) = 2

No. of days
D_(2) = ??

No. of hours taken
H_(2) = 5 hours

We know that


M_(1)
D_(1)
H_(1) =
M_(2)
D_(2)
H_(2)

⇒ Put all the values in above formula we get

⇒ 10 × 5 × 2 = 2 ×
D_(2) × 5


D_(2) = 10 days

Thus the no. of days required to finish the work = 10 days