A project manager is managing a project that has reached the end of planning phase. The work scope has been agreed to and definitive cost estimates have been completed for the project. The total estimated cost of the project is $100,000. It is reasonable to expect that the project will not cost over which of the following value?

a. $100,000
b. $110,000
c. $125,000
d. $175,000

asked
User HalR
by
8.6k points

1 Answer

5 votes

Answer:

125

Step-by-step explanation:

It waz the totale over estimate