asked 109k views
19 votes
a contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?​

1 Answer

8 votes

Answer:

225 men

This conversion leads to the answer:

  • 30 days → 150 men
  • 1 days → (150 *30) men
  • 1 days → 4500 men
  • 20 days → (4500/20) men
  • 20 days → 225 men
answered
User Xll
by
7.7k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.