asked 42.8k views
5 votes
On a construction project, you estimate a total of 80 hours of labor. You will work 40 of the hours. Assistant A will work 25 hours. Assistant B will work the remaining hours. You earn $22 per hour. Assistant A earns $15 per hour. Assistant B earns $10 per hour. Altogether, how much is labor going to cost for this project?

asked
User Yekanchi
by
8.3k points

1 Answer

6 votes

Answer:

$1,630

Explanation:

Assistant 2 hours: 80-40-25 = 15

YOU: 22 x 40 = $880

ASSISTANT 1: 15 x 25 = $375

ASSISTANT 2: 10 x 15 = $150

880+375+150 = $1,630

answered
User Cajwine
by
8.0k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.