. Resource utilization charts based on each activity’s latest start time are said to be based on an ____ schedule. a. as-soon-as-possible b. as-late-as-possible c. as-needed d. as-flexible-as-possible

asked
User Mapad
by
7.5k points

1 Answer

4 votes

Answer:

The correct answer is letter "B": as-late-as-possible.

Step-by-step explanation:

Primavera P6 is a Project Management Program useful to plan, schedule, execute, and control projects. In scheduling, there are constraints such as the As-Late-As-Possible (ALAP) which is used to delay a project's start without affecting its completion. For manufacturers using the Just-In-Time (JIT) inventory ALAP will be beneficial since the arrival of the raw materials must be delayed until it reaches the plant.