asked 215k views
5 votes
Which EST graph correctly represents the information on the table ​

Which EST graph correctly represents the information on the table ​-example-1

1 Answer

1 vote

Answer:

the first one

Explanation:

A graph showing the Earliest Start Times (EST) for project tasks is computed left to right based on the predecessor task durations. For dependent tasks, the earliest start time will be the latest of the finish times of predecessor tasks.

The first graph appears to appropriately represent the table values, using edges to represent task duration, and bubble numbers to represent start times.

The second graph does not appropriately account for duration of predecessor tasks.

The third graph seems to incorrectly compute task completion times (even if you assume that the edge/bubble number swap is acceptable).

Which EST graph correctly represents the information on the table ​-example-1
answered
User Cbll
by
8.3k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.