Using the Time-Cost CPM model, the crash time is the shortest possible time allowed for each activity in the project. Group of answer choices True False

1 Answer

5 votes

Answer:

The answer is true

Step-by-step explanation:

The Critical Path Method (CPM) is a project scheduling technique to analyze and represent the tasks involved in completing a given project. The critical path method assumes that the duration of an activity depends on the amount of resources assigned to it. Crash duration in CPM is the minimum duration of the activity.