Risks _______ should be given higher priority because if the risk occurs, it would have a greater impact on the schedule than if it was associated with activities on a path that has a large positive value of total slack.a. that occur first in the projectb. that affect the most costly activitiesc. on the critical pathd. that affect the activities near the end of the project

asked
User Plonser
by
8.3k points

1 Answer

6 votes

Answer: c. On a critical path

Step-by-step explanation:

Risks on a critical path should be given higher priority, this is considering the situation of the risk.