A function within a project plan that shows a list of project tasks that must be completed on time, so that a delay does not delay the overall project. a. Gantt chart b. POAM c. Milestone plan chart d. Critical path chart

asked
User Viclim
by
7.3k points

1 Answer

6 votes

Answer:

The correct option is D: Critical Path

Step-by-step explanation:

The critical path of a project encompasses a list of task linked in such a way that they directly impact the finish date of the project. No task on the critical path is expected to be late, else the whole project will also be late. It also shows the tasks which has to be completed timely in order for a project to also finish on the scheduled date.