asked 25.9k views
3 votes
The addition of acceptance criteria factors to the milestone schedule in a project charter helps the team understand who will judge the quality of the deliverable associated with each milestone, and:______

asked
User Renke
by
7.4k points

1 Answer

3 votes

Answer: The criteria or standards they will use.

Explanation: Project Charter is a major component of project management system,the project charter Describes the roles and responsibilities of the team members,the task descriptions,the time lines,it is an important and reference for both present and future projects.

The project Charter also sets the project deliverables with each mile stone,the criteria and standards through which the project deliverables associated with each milestone will be judged.