The Incident Action Plan is prepared by General Staff from which section? A. Planning B. Operations C. Logistics D. Finance/Administration

asked
User Prnsml
by
7.6k points

2 Answers

2 votes

Answer:A

Explanation:i don't know

answered
User Sabeen
by
8.8k points
0 votes

Answer:

The correct answer is A

Step-by-step explanation:

IAP stands for Incident Action Plan, which is defined as the organized course of the events that addresses or notices all the phases or stages of the incident control in the specified time.

It is required to completed or finished in the timer period or time frame, which allows the least amount of the action that is negative to continue.

So, this plan is made or prepared through the General Staff of the Planning section.