What type of cost is incurred when a project must be conducted faster than normal, and overtime for workers and / or extra charges for rapid delivery from suppliers are necessary?

1 Answer

3 votes

Answer:

Expedited costs

Step-by-step explanation:

Expedited costs is the cost or an expense which is defined as the extra cost or an additional cost like higher early prices, overtime and express freight. This cost is incurred in order to fast the tracking replacement or repairs of the damaged assets or lost assets. These kinds of the expenses are not covered under the normal fire insurance policy until specifically included.

Therefore, the expedited cost is incurred when the project need to be performed faster than usual and the overtime for the workers as well as the additional charges are paid for fast delivery from suppliers.

answered
User Woody
by
8.9k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.