A work breakdown structure typically is developed in which project management process group? a) Planning. b) Directing and managing project work. c) Monitoring and controlling project work. d) Executing.

asked
User Shuduo
by
8.4k points

1 Answer

5 votes

Answer:

(a) Planning

Step-by-step explanation:

The work breakdown structure consists of the tasks required to accomplish a project goal, arranged into sections.

It is usually developed at the planning stage of project management, before other project activities are carried out.