PS.74 Bell computer is planning to launch a new high-end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be 90 units and there are three 8-hour shifts available each day to meet this production quota. 
 Task 
 Req'd Time (in minutes) 
 Predecessor 
 A 
 12 
 None 
 B 
 13 
 A 
 C 
 5 
 B 
 D 
 4 
 B 
 E 
 13 
 A 
 F 
 6 
 C,D 
 G 
 7 
 F 
 H 
 11 
 E 
 I 
 6 
 G,H 
 What is the total time, in minutes, to produce one server? 
 What is the takt time (in minutes) for this production line? (Your answer should be a whole number.) 
 What is the theoretical minimum number of workstations required for this production line? (Round up your answer to the nearest whole number.) 
 After assigning task A to workstation 1, which task (or tasks) should you assign to workstation 2? (In the field below, write the number that corresponds to your answer. Do not put a period after the number.) 
 B 
 C 
 D 
 E 
 B or E 
 C and D 
 Suppose you assign task B to workstation 2, which task (or tasks) should you then attach to workstation 3? (In the field below, write the number that corresponds to your answer. Do not put a period after the number.) 
 E and H 
 E 
 E or C, D, and F 
 C and D 
 Assume you assign tasks C, D and F to workstation 3, task E to workstation 4, which task (or tasks) should you assign to workstation 5? 
 G and H 
 G and I 
 H and I 
 H 
 What is the cycle time (in minutes) for this production line? 
 What is the overall efficiency for this production line? (percentage)