Program Evaluation Review Technique (PERT) is a _____ technique because it analyzes a large, complex project as a series of individual tasks.

1 Answer

5 votes

Answer:

scheduling technique

Step-by-step explanation:

Project Evaluation Review Technique and Critical Path

Method (CPM) are scheduling techniques used to plan, schedule,

budget and control the many activities associated with projects.

Projects are usually very large, complex, custom products that

consist of many interrelated activities to be performed either

concurrently or sequentially.