cost formula is expressed as follows: Y = $17PH + $760,000 where PH is defined as process hours. What budgeted dollar amount would appear in DT's static budget and flexible budget for the preceding cost formula?

1 Answer

3 votes

Answer:

B. $ 1,984,000 $ 2,112,000

Step-by-step explanation:

Static budget is a budget that has been prepared for a standard level of output with no tendency to vary irrespective of the level of output.

Therefore, the figure that will appear in static budget is as follows:

Y = $16PH + $640,000 where PH is defined as process hours

PH = 84,000 (Budgeted output)

Y = $16(84,000) + $640,000

Y = $1,344,000 + $640,000

Y = $1,984,000

That is the figure that will appear in the static budget is $1,984,000

Flexible budget is a budget designed to vary with the level of actual activity.

Therefore the figure that will appear in the flexible budget is as follows:

Y = $16PH + $640,000 where PH is defined as process hours

PH = 92,000 (Budgeted output)

Y = $16(92,000) + $640,000

Y = $1,472,000 + $640,000

Y = $2,112,000

That is the figure that will appear in the flexible budget is $2,112,000

answered
User Leyda
by
8.1k points

Related questions

asked Jan 12, 2024 10.4k views
ManxJason asked Jan 12, 2024
by ManxJason
9.2k points
1 answer
5 votes
10.4k views
asked Dec 11, 2024 209k views
Jacoballenwood asked Dec 11, 2024
by Jacoballenwood
7.7k points
1 answer
0 votes
209k views
asked Mar 16, 2024 59.7k views
Treaschf asked Mar 16, 2024
by Treaschf
7.9k points
1 answer
4 votes
59.7k views
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.