asked 51.6k views
5 votes
If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy?

asked
User Gtu
by
8.0k points

1 Answer

4 votes

Answer:

Full funding policy.

Step-by-step explanation:

This would be a violation of Full funding policy.

Full funding strategy is a federal budgeting requirement implemented by Congress in the 1950s on the Department of Defense (DOD) that mandates all acquisition expenses of a weapons or piece of military equipment to be financed in the year the object is procured. Hence in the above example there is violation of Full funding strategy.

answered
User MojoDK
by
8.3k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.