asked 196k views
0 votes
What is the typical impact on a program's cost and schedule when unstable requirements lead to changes late in the system's development?[Identify how instability of requirements, design, and production processes impact program cost and schedule.]

a. Significantly negative impact on cost and schedule
b. Marginally negative impact on cost and schedule
c. Negative impact on cost; no impact on schedule
d. No impact on cost; negative impact on schedule

asked
User Grrigore
by
8.4k points

1 Answer

1 vote

Answer: The correct answer is "a. Significantly negative impact on cost and schedule".

Explanation: The typical impact on a program's cost and schedule when unestable requirements lead to changes late in the system's development is the significantly negative impact on cost and schedule.

answered
User Skafle
by
8.7k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.