In a _____ organizational structure, project managers work full-time on projects, while team members report to both functional managers and project managers.

1 Answer

3 votes

Answer:

The correct answer is letter "D": strong matrix.

Step-by-step explanation:

A strong matrix organization is one in which employees have two managers: the functional manager and the project manager. Authority is shared between these two and the approach aims to achieve balance in the hierarchy of each of them. In this type of organization project managers tend to work full time as well as most of the company's personnel.