A company makes a profit of $75 per software program and $125 per video game. The company can produce at most 350 software programs and at most 200 video games per week. Total production cannot exceed 475 items per week. How many items of each kind should be produced per week in order to maximize the profit?

asked
User Bcherry
by
7.5k points

1 Answer

3 votes

Answer: 200 video games and 275 software programs for a maximum profit of $45,625

Explanation:

475 - 200 = 275

200 times 125 = 25000

275 times 75 = 20625

Maximum profit per week = $45,625