Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job? ​

asked
User MyICQ
by
8.6k points

1 Answer

1 vote

Answer:

15

Explanation:

30 men = 20 days

40 men= ?

1man =30×20= 600

=600÷40= 15

40 men = 15 days