36 workers can complete a piece of work in 12 days how many workers should be removed to complete the same work in 24 days

please explain step by step​

2 Answers

4 votes
18. They multiplied the amount of days by 2, so you divide the amount of workers by 2. This is reverse/opposite operations. I hope this helps :)