12 men finish work=24 days, 8 men finish work=how many days?

asked
User Lapsus
by
7.4k points

1 Answer

2 votes
12 multiply 2 we get 24
That way we will do 8
8 multiply 2 we get 16

16 is the ans
Hope this is helpful