asked 39.5k views
2 votes
The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________.

a. range estimating.
b. phase estimating method.
c. WBS method.
d. template method.
e. parametric procedure.

1 Answer

1 vote
B range eliminating the property for the property is right