asked 70.5k views
3 votes
Lesco's is evaluating a project that has a different level of risk than the overall firm. This project should be evaluated: Group of answer choices

asked
User Hpaulj
by
8.7k points

1 Answer

5 votes

Answer:

3. using a beta commensurate with the project's risks.

Step-by-step explanation:

In the case when the project is evaluated so there is the different type of the risk instead of the total firm so here the project should be evaluated via beta commensurate alonhg with the risk of the project. As each and very project has the different level of risk also there is a different between the beta as if we compared to the beta of the market, beta of the firm etc

Hence, the above represent the answer

answered
User Timmmmmb
by
8.1k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.

Categories