The theory of constraints says thatqueues should not be allowed to form in the plant.bottleneck resources should be idle whenever possible.the bottleneck is the most critical resource.labor expense reduction should be the primary goal.

1 Answer

2 votes

Answer:

the bottleneck is the most critical resource

Step-by-step explanation:

The constraint theory represent that the bottleneck would be considered as the most critical resources as it decided how much long the process could be delayed and due to this the objectives and the goals of the organization would be highly impacted