asked 221k views
1 vote
Which stage in project management involves team members working on the assigned tasks as described in the project plan?

A.
initiation
B.
monitoring
C.
execution
D.
closure
E.
planning

1 Answer

4 votes

Answer:

C. execution

Step-by-step explanation:

  • The execution stage is 3rd stage in project management lifecycle is usually is longest phase as during which the teams develops the product or services and presents the final end product to the clients. Here the team members work on the same set of guidelines that are assigned or designed in a project.
answered
User Yanes
by
7.9k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.

Categories