BBonita Inc. sells a high-speed retrieval system for mining information. It provides the following information for the year.

Budgeted Actual
Overhead cost $1,333,200 $1,307,200
Machine hours 56,300 49,000
Direct labor hours 101,000 97,800
Overhead is applied on the basis of direct labor hours. Compute the predetermined overhead rate.

asked
User YusufUMS
by
8.4k points

1 Answer

2 votes

Answer:

$23.68 per machine hour

Step-by-step explanation:

Given the above information, the predetermined overhead rate is computed as

= Budgeted overhead cost / Estimated number of machine hours

Budgeted overhead cost = $1,333,200

Estimated number of machine hours = 56,300

Therefore,

Predetermined overhead rate

= $1,333,200 / 56,300

Predetermined overhead rate= $23.68 per machine hour