asked 197k views
3 votes
Harold works as an operations manager. He uses a project management tool to schedule and manage the steps of the manufacturing process. Harold has made a list of all the activities involved in the process. He has calculated the optimistic time, most likely time, and pessimistic time that the process might take to be completed. Which project management tool is Harold using?

A.
Critical Path Method (CPM)
B.
Program Evaluation and Review Technique (PERT)
C.
Total Quality Management (TQM)
D.
Gantt chart
E.
Just In Time (JIT)

2 Answers

3 votes

Answer:

PERT

Step-by-step explanation:

Plato/Edmentum

answered
User Nakhodkin
by
8.7k points
5 votes

Answer:

B

Step-by-step explanation:

answered
User Nantitv
by
8.0k points