In a project schedule, which types of dependencies are most common?

2 Answers

5 votes
Finish to start dependency- This is the most common type of dependency in project management as well as real life.
answered
User Yana
by
8.1k points
2 votes

Answer:

Finish to Start, finish to finish.

Step-by-step explanation:

answered
User Han Zhengzu
by
8.2k points