At Eady Corporation, maintenance is a variable overhead cost that is based on machine-hours. The performance report for July showed that actual maintenance costs totaled $10,370 and that the associated rate variance was $340 unfavorable. If 5,900 machine-hours were actually worked during July, the standard maintenance cost per machine-hour was:

asked
User Ajmal VH
by
8.2k points

1 Answer

3 votes

Answer:

See below

Step-by-step explanation:

$10,370 - $340 = $10,030