If 6 workers take 700 hours to finish a project, how long will it take 12 workers to complete the same project?

asked
User Verushka
by
8.0k points

2 Answers

5 votes
12/6 = 2
700/2 = 350
There are double the amount of workers so it is half the time.
answered
User Eric Skiff
by
8.7k points
1 vote

Answer:

350 hours

Explanation:

answered
User Sramu
by
8.4k points