asked 78.2k views
2 votes
Choose the correct answer.

The time to complete a project varies inversely with the number of employees. If 6 people can complete the project in 4 days, how long will it take 8 people?

A. 5 days
B. 3 days
C. 2 days
D. 6 days

asked
User Stirredo
by
8.3k points

2 Answers

12 votes
if 6 complete that in 4 days then 1 man completes it in 24 days. So 8 men would complete the work in 3 days.
answered
User Paul Gerarts
by
7.8k points
3 votes
Answer is option c which is 2 days
answered
User Sesmic
by
8.5k points