ackson manufactures products x and y, applying overhead on the basis of labor hours. x, a low- volume product, requires a variety of complex manufacturing procedures. y, on the other hand, is both a high-volume product and relatively simplistic in nature. what would an activity-based costing system likely disclose about products x and y as a result of jackson's current accounting procedures?

1 Answer

1 vote

Answer:

X- Undercosted

Y -Overcosted

Step-by-step explanation: