asked 69.4k views
1 vote
Diego can lay a slab of concrete in 15 hours, while Luis can do it in 12 hours. If Diego and Luis work together, how long will it take?

asked
User Annakaye
by
8.2k points

1 Answer

7 votes

Answer: t = 6.67 hours

Step-by-step explanation:

From the information given,

Diego can lay a slab of concrete in 15 hours. This means the rate at which he can lay the slab = 1/15

Luis can do it in 12 hours. The rate at which he lay the slab = 1/12

Let t represent the number of hours it will take them to work together. It means that the rate at which they can lay the slab together is 1/t

Since the rates are independent of each other, then

1/15 + 1/12 = 1/t

The lowest common multiple of the denominator is = 60

Thus,

(4 + 5)/60 = 1/t

9/60 = 1/t

By taking reciprocal of both sides,

t = 60/9

t = 6.67

It will take 6.67 hours for them to work together

answered
User Steven Green
by
7.8k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.